A.
Piping
1.
Piping in
boiler and mechanical
rooms less than 1 1/4" (32mm) inside diameter.
2.
All other
piping less than 2
1/2" (64mm) inside diameter.
3.
All
piping suspended by individual
hangers 12" (300mm) or less as measured from the top of the pipe to the
bottom of the support where the hanger is attached. However, if the 12"
(300mm) limit is exceeded by any hanger in the run, seismic bracing is
required
for the run.
The 12"
(300mm) exemption
applies for trapeze supported systems if the top of each item supported
by the
trapeze qualifies.
B.
Ductwork
1.
Rectangular
and square and ducts
that are less than 6 square feet in cross sectional area.
2.
Oval
ducts that are less than 6
square feet (.5m2) in cross sectional area based on nominal size.
3.
Round
duct less than 28"
(.5m2) in diameter.
4.
All duct
suspended by hangers
12" (300mm) or less in length as measured from the top of the duct to
the
point of attachment to the structure.
Hangers must be attached within 2" (50mm) of the top of the duct
with a minimum of two #10 sheet metal screws.
If the 12" (300mm) limit is exceeded by any hanger in the run,
seismic bracing is required for the run.
C.
Suspended equipment
1.
VAV boxes
and fan powered equipment
weighing less than 50 lbs. (23kg) and rigidly connected to the supply
side of
the duct system and supported with a minimum of 4 hanger rods.
D.
Electrical
1.
All conduits
less than 2 1/2" (64mm) diameter suspended by individual hanger rods.
2.
All
conduits suspended by
individual hangers 12" (300mm) or less as measured from the top of the
conduit to the bottom of the support where the hanger is a attached. However, if the 12" (300mm) limit is
exceeded by any hanger in the run, seismic bracing is required for the
run.
The 12"
(300mm) exemption
applies for trapeze supported systems if the top of each item supported
by the
trapeze qualifies.